These entry systems are available in widths from 900 mm to 1.100 mm and are manufactured in various versions Offered to meet diverse customer requirements, integrated hazard detection via sensors and electric ramp extension ensure additional safety and convenience.
As an internationally operating, family-run group of companies, HÜBNER's success is largely based on the long-standing expertise and high loyalty of its employees.
Project reason & objective
Adapting to new guidelines and regulations made a comprehensive revision and further development of the electric ramps necessary. Consequently, the existing assembly jig, a custom-built design for frame production, could no longer be used. It was not only too large in its dimensions, but also no longer offered a flexible working height.
Thus, the A need exists for a new, modern assembly aid. The choice for the planning and construction of the new assembly structure quickly fell on the company CREFORM. This was because Hübner already have good experiences with Creform work aids had done and is very satisfied with its quality.
This project took into account both the new legal requirements and the specific needs of the production staff. The overarching goal was to create an optimal working environment, improve ergonomics, and significantly increase productivity.
Requirements
- Compact design to save space
- Telescopic design to accommodate all frame variants
- Height adjustment for ergonomic adaptation of the assembly station to different body sizes
- Battery-powered height adjustment to avoid cables (freestanding solution)
- 180° rotation for easy installation of both ramp sides
- Optimized weight distribution for an optimized weight distribution of the workpiece, closer to the rotation point for easier, more controlled turning without a counterweight.
Project implementation & assembly process
Within only six weeks The project was successfully completed from initial inquiry to implementation. Standard products and the first prototypes have already been assembled on the assembly aid to test and further optimize the design.
The production of the electric ramps takes place in several steps:
1. Assembly of the outer frame
2. Installation of the internal components including sensors, warning tone and lighting
3. Integration of the flap – the component is completed within one hour.
During assembly, the entire structure can be rotated 180° , which makes the work significantly easier.
Optimization & Challenge
The company relied on CREFORM because Several solutions are already successfully in use These include trolleys and mobile material racks. As part of the ongoing design development, the Lifting capacity Adapted to the increased requirements. The extension of the lifting height from 300 mm to 400 mm ensures that future modifications can also be implemented without any problems.
Key challenges in the planning process included:
- Precise pipe connection through internal guidance with different pipe diameters
- Compact integration of two drive motors including central control unit
- Constructive combination of square and round tube profiles for optimal functionality
- Stable and collision-free swiveling of the workpiece within the base frame
Successful implementation and future prospects
The developed assembly structure particularly impressed the employees because of:
- The rotating device in combination with the height adjustment ensures ergonomic working conditions.
- The compact design saves valuable space in production.